Written Answers
Motorways: Repairs and Maintenance
Asked by: Huw Merriman (Conservative - Bexhill and Battle)
Thursday 24th March 2022

Question to the Department for Transport:

To ask the Secretary of State for Transport, with reference to paragraphs 18 to 21 of the Government Response to the Transport Select Committee’s Third Report on the Rollout and safety of smart motorways, HC 26, published on 12 January 2022, whether (a) motorway service stations, (b) slip roads and (c) hard shoulders are defined as emergency refuge areas by National Highways in its work retrofitting all-lane running motorways.

Answered by Trudy Harrison

In the Government’s response to the Transport Committee report published in January 2022, we announced that we would be committing £390 million to add around 50% more places to stop in an emergency by 2025, giving drivers added reassurance. National Highways is currently developing a detailed programme of work which will set out the type and location of emergency areas to be delivered.

Motorways: Repairs and Maintenance
Asked by: Sarah Champion (Labour - Rotherham)
Monday 29th November 2021

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether contracts have been issued for smart motorway projects on the (a) M62, (b) M40 and (c) M42 as of 24 November 2021; and what his planned timetable is for commencing that work on those motorways.

Answered by Trudy Harrison

We are currently considering the Transport Committee’s recommendations contained in its report, Rollout and safety of smart motorways, and their practical applications, and will be providing a formal response in due course.

Contracts have been previously issued for smart motorways projects on the (a) M62 Junctions 20 to 25 and the M40/M42 Interchange, which is treated as one scheme.

Early design and enabling works contracts were awarded in early 2019 for the M62 Junctions 20 to 25 and M40/M42 Interchange, with work commencing late 2019. This included detailed surveys, hard shoulder strengthening and limited site clearance. Full detailed design was awarded on 11 June 2020 followed by full construction works on 23 October 2020 through a package contract to the Smart Motorways Alliance.

Main construction works for the M62 Junctions 20 to 25 is scheduled for January 2023. Main construction works for the M40/42 Interchange commenced in October 2021 with limited vegetation clearance and ecological mitigation for communications cable diversions.